Kitchen extension: the build in order

A kitchen extension is one of the most common projects there is, and also one of the most disruptive. Knowing the order things happen in makes the whole thing less of a mystery and helps you plan around it.

Before anything starts

The groundwork happens before the groundwork. Drawings, any planning or permitted development checks, Building Regulations approval, structural calculations and, where needed, party wall notices all come first. Windows, doors and any steelwork often have lead times, so they are usually ordered early. It is common for this stage to take longer than the build itself.

Site set-up and groundworks

The site is made safe, the garden is protected where possible and the footprint is set out. Foundations are dug and inspected by building control before concrete goes in. Drains that cross the area are located and, if necessary, diverted or protected. This is the stage where hidden surprises such as old pipes or soft ground most often turn up.

Floor and walls

A ground-bearing or suspended floor is built, with a damp-proof membrane and insulation, and the walls come up to the height of the new roof. Where the extension joins the house, an opening is formed in the existing wall and a steel or other structural beam is installed with temporary supports while it goes in. This is the noisiest and dustiest part for anyone living in the house.

Roof and weathertight

The roof structure goes on, followed by the covering and any rooflights. Windows and doors are fitted. Once the building is weathertight, the inside work can continue regardless of the weather, which is why this point is a milestone worth asking about.

First fix

Electricians, plumbers and heating installers run cables and pipes before the walls are closed up. Decisions made earlier about socket positions, lighting, underfloor heating and the location of the sink and hob matter here, because moving them later is expensive. Building control may inspect certain elements at this point.

Plastering, screed and drying time

Walls are plastered and floors may be screeded. Both need time to dry before the next stage, and rushing them can cause cracking or problems with floor finishes. This is often the quiet part of the job where it looks as if little is happening, but it is doing necessary work.

Second fix and kitchen fitting

Kitchen units, worktops, tiling, electrical fittings, plumbing connections and decorating happen last. Kitchen suppliers' lead times are a common cause of delay, so confirm the delivery date well in advance and check what condition the room needs to be in for fitting to start.

Decisions to make early

The choices that cause most trouble when left late are the kitchen layout, the position of the sink and hob, the type and number of windows and doors, whether the floor will be heated and where the sockets and lights go. Visit a kitchen supplier before first fix, even if you are not buying yet, so that the layout drawings the electrician and plumber work from are real rather than guessed. A short list of finish choices made early saves a lot of waiting later.

What affects the timeline

Weather during groundworks and roof stage, late deliveries, design changes once work is underway and unexpected findings in the ground or the existing walls are the usual causes of delay. A realistic programme will say what the plan is and what could move it. Be wary of any timeline that promises a fixed number of weeks without a visit to the property.

Related pages

Free site visit and quote

Tell us about the project at hello@sandwichbuilders.co.uk or on WhatsApp. We'll arrange a site visit to give you a proper quote.

Tell us what you're planning. We'll tell you what it takes.

Free, no-obligation site visit and quote. Describe the project, send photos of the space if you can, and we'll arrange a visit to scope it properly.